Budgeted variable overhead for the year is $130,000.Expected activity is 20,000 standard direct labour hours.The actual hours worked were 18,250,and the standard hours allowed for actual production were 19,750.What was the variable overhead efficiency variance?


A) $0
B) $1,500 F
C) $9,750 F
D) $12,000 F