Multiple Choice
Allan Company manufactures overalls. During the year, it manufactured 125,000 overalls, using 2.9 hours of direct labour at a rate of $6.25 per hour. The materials and labour standards for manufacturing the overalls are as follows:
Allan required 600,000 m at $1.95 per metre to make the 125,000 overalls.
-Refer to the Figure.What is the entry to record the issuance and usage of materials?
A) Work in Process 1,170,000Materials Usage Variance 48,750Materials 1,218,750
B) Work in Process 1,200,000Materials Usage Variance 50,000Materials 1,250,000
C) Work in Process 1,218,750Materials Usage Variance 48,750Materials 1,170,000
D) Work in Process 1,250,000Materials Usage Variance 50,000Materials 1,200,000
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Match each of the following terms with
Q21: The total budget variance is the difference
Q104: The Fantastic Tool Company (Mexico Division) produced
Q105: During April, Risco Company produced 13,00012,000 chainsaw
Q110: Baker Company adopted a standard cost
Q111: Perfect Builders constructs houses. The standard labour
Q112: During March, a small roofing company purchased
Q114: How do standard cost systems enhance operational
Q127: Match each of the following calculations with
Q131: Ideal standards demand maximum efficiency and can