Multiple Choice
Allan Company manufactures overalls. During the year, it manufactured 125,000 overalls, using 2.9 hours of direct labour at a rate of $6.25 per hour. The materials and labour standards for manufacturing the overalls are as follows:
Allan required 600,000 m at $1.95 per metre to make the 125,000 overalls.
-Refer to the Figure.What is the entry to record the direct labour variances?
A) Work in Process 2,265,625Labour Efficiency Variance 75,000Labour Rate Variance 90,625Accrued Payroll 2,250,000
B) Work in Process 2,250,000Labour Rate Variance 90,625Labour Efficiency Variance 75,000Accrued Payroll 2,265,625
C) Work in Process 2,250,000Labour Rate Variance 93,750Labour Efficiency Variance 78,125Accrued Payroll 2,265,625
D) Work in Process 2,265,625Labour Efficiency Variance 78,125Labour Rate Variance 93,750Accrued Payroll 2,250,000
Correct Answer:

Verified
Correct Answer:
Verified
Q29: To determine whether variances are significant, managers
Q85: The sum of the material price and
Q87: Which of the following is NOT characteristic
Q88: Which of the following standards are based
Q89: During March,6,000 direct labour hours were worked
Q92: RJB Builders makes mouldings.Its standard quantity of
Q93: Of the three cost reduction methods typically
Q94: The standard quantity of materials allowed can
Q137: Matching<br>Match each item with the correct statement
Q171: Which formula is used to calculate the