The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: What is the amount of the factory overhead controllable variance?
A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q8: Standard costs are used in companies for
Q30: Ruby Company produces a chair that requires
Q32: If the standard to produce a given
Q67: The following data relate to direct labor
Q68: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2083/.jpg" alt=" Calculate the fixed factory
Q73: The standard costs and actual costs for
Q74: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2083/.jpg" alt=" Calculate the total
Q89: If the wage rate paid per hour
Q113: The formula to compute direct labor time
Q164: At the end of the fiscal year,