A Project Has an IRR of 16% and Is Being

Question 161

Multiple Choice

A project has an IRR of 16% and is being considered by a firm with $5 million in debt and $15 million in equity. Assuming the debt costs 12% (after-tax value) , what is the most equity can cost for the project to be acceptable to the firm? (hint: set the IRR equal to WACC)


A) 18.25%
B) 17.83%
C) 17.33%
D) 16.89%