Multiple Choice
A city starts a solid waste landfill during 2010. When the landfill was opened the city estimated that it would fill to capacity within 5 years and that the cost to cover the facility would be $1.5 million which will not be paid until the facility is closed. At the end of 2010, the facility was 20% full, and at the end of 2011 the facility was 45% full. If the landfill is judged to be a governmental fund, what liability is reported on the fund financial statements at the end of 2011?
A) $0.
B) $300,000.
C) $375,000.
D) $600,000.
E) $675,000.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: The City of Wetteville has a fiscal
Q4: The Town of Wakefield opened a solid
Q4: Which statement is false regarding the Balance
Q5: Marie Todd works for the City of
Q6: A five-year lease is signed by the
Q9: Which criteria must be met to be
Q10: The employees of the City of Raymond
Q11: A city starts a solid waste landfill
Q19: What is meant by the term legally
Q43: A method of depreciation for infrastructure assets