Multiple Choice
Harry Company's standard variable overhead rate is $6 per direct labor hour, and each unit requires 2 standard direct labor hours. During March, Harry recorded 6,000 actual direct labor hours, $37,000 actual variable overhead costs, and 2,900 units of product manufactured. What is the total variable overhead variance for March for Harry?
A) $1,200 U
B) $600 U
C) $1,000 U
D) $2,200 U
Correct Answer:

Verified
Correct Answer:
Verified
Q28: A static budget is best used to<br>A)
Q30: Favor Company budgeted the following amounts:<br> <img
Q31: The _ is the difference between the
Q34: For activity flexible budgeting, a cost formula
Q35: The formula for calculating the variable overhead
Q37: Gallant Company uses standard costing. Overhead is
Q105: An after-the-fact flexible budget allows managers to
Q158: A budget prepared for a particular level
Q175: Fixed overhead was budgeted at $84,000 and
Q176: A static budget compares actual cost with