Multiple Choice
Figure 15-1 The following information relates to Markely Manufacturing:
To produce a unit of product: There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
-
Refer to Figure 15-1.How long would it take to process the first unit of a 20-unit batch under a cellular manufacturing setup?
A) 23 minutes
B) 17 minutes
C) 50 minutes
D) 15 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q19: The order fulfillment value stream focuses on<br>A)developing
Q71: _ is(are) productivity measure(s) in which inputs
Q72: _ is(are) productivity measure(s) that are expressed
Q73: Using average product cost for a value
Q79: What is the usual formula for calculating
Q79: Figure 15-4 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2043/.jpg" alt="Figure 15-4
Q80: Information about Gausen Company is as follows:
Q81: Information about Blair Company is as follows:
Q136: Discuss the advantages and disadvantages of partial
Q145: What approach is normally used to calculate