Solved

Figure 15-2 the Following Information Relates to Ramesy Manufacturing

Question 66

Multiple Choice

Figure 15-2 The following information relates to Ramesy Manufacturing:
To produce a unit of product:
Figure 15-2 The following information relates to Ramesy Manufacturing: To produce a unit of product:   There is a wait time of 5 minutes before the cutting department begins a batch, 15 minutes between the cutting and welding departments, a move and pre-wait between welding and polishing of 12 minutes, and a move and pre-wait between the polishing and finishing departments of 8 minutes. - Refer to Figure 15-2.What is the cycle time of operation? A)  35 minutes B)  20 minutes C)  60 minutes D)  16 minutes There is a wait time of 5 minutes before the cutting department begins a batch, 15 minutes between the cutting and welding departments, a move and pre-wait between welding and polishing of 12 minutes, and a move and pre-wait between the polishing and finishing departments of 8 minutes.
-
Refer to Figure 15-2.What is the cycle time of operation?


A) 35 minutes
B) 20 minutes
C) 60 minutes
D) 16 minutes

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions