Figure 15-2 The following information relates to Ramesy Manufacturing:
To produce a unit of product: There is a wait time of 5 minutes before the cutting department begins a batch, 15 minutes between the cutting and welding departments, a move and pre-wait between welding and polishing of 12 minutes, and a move and pre-wait between the polishing and finishing departments of 8 minutes.
-
Refer to Figure 15-2.If Ramesy produces in batches of 10 units, how much time would have elapsed by the time the 10th unit is produced under a manufacturing cell environment (assuming the cell is processing continuously) ?
A) 65 minutes
B) 60 minutes
C) 150 minutes
D) some other amount
Correct Answer:

Verified
Correct Answer:
Verified
Q55: At the end of 2011, Gilley Company
Q56: Total productive efficiency is the point at
Q57: The following information relates to Quaker Manufacturing:<br>To
Q58: One way to identify value streams is
Q59: With multiple products in a value stream,
Q61: Figure 15-1 The following information relates to
Q62: _ is the difference between the total
Q63: At the end of 2011, Carianne Corporation
Q64: Hieber Company produces pants that use two
Q65: Information about Blum Company is as follows: