Multiple Choice
Each unit of product requires 16 pounds of material.Due to scrap and rework, each unit has been averaging 18 pounds of material.The material costs $4 per pound.
-The non-value-added costs are
A) $4.
B) $8.
C) $64.
D) $72.
Correct Answer:

Verified
Correct Answer:
Verified