Multiple Choice
Suppose that a firm makes gears (G) and axles (A) . Each gear requires 15 minutes of labor and each axle requires 30 minutes of labor. One thousand hours of labor are available. How should the labor constraint(s) be written?
A) G + A ≤ 1000
B) .25G + .5A ≤ 1000
C) G ≤ 15 and A ≤ 30
D) .25G + .5A ≥ 1000
E) 15G + 30A ≤ 1000
Correct Answer:

Verified