Multiple Choice
What establishes a point of time in the future inside of which changes must be made by the master scheduler, and changes outside of which can be changed by system logic?
A) demand time fence
B) supply time fence
C) system time fence
D) frozen time fence
E) planning time fence
Correct Answer:

Verified
Correct Answer:
Verified