Multiple Choice
In the "liquid" portion of the MPS, the master scheduler generally has the authority to approve what changes?
A) product mix
B) changes needing extra resources (already authorized by the aggregate plan)
C) product mix and changes needing extra resources (already authorized by the aggregate plan)
D) neither product mix and changes needing extra resources (already authorized by the aggregate plan) e) there is not such a thing as a "liquid" portion of the MPS
Correct Answer:

Verified
Correct Answer:
Verified