    Exam 20: Master Scheduling and Rough-Cut Capacity Planning
  5. Question
    A Negative Number in the Available-To-Promise Row Is ___________ a Problem
Solved

A Negative Number in the Available-To-Promise Row Is ___________ a Problem

Question 32

Question 32

Multiple Choice

A negative number in the available-to-promise row is ___________ a problem.


A) sometimes
B) always
C) usually
D) never
E) 25%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q27: Consider the following partial MPS record. Beginning

Q28: The Master Production Schedule is often stated

Q29: Changes to the MPS that are requested

Q30: CPOPF is the acronym for Capacity Planning

Q31: Discuss how the MPS is evaluated in

Q33: Consider an MPS record. An MPS shipment

Q34: Consider the following partial MPS record. Beginning

Q35: What is the formula for calculating the

Q36: Consider the following partial MPS record. Beginning

Q37: What establishes that point of time in

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines