Multiple Choice
Johnny Now, Inc. produces two different models of outhouses. Demand next period is expected to be 12,000 and 18,000 units for Models A and B, respectively. Model A has CPOPF planning factors of 0.75 and 0.60 for direct labor and machine time, respectively. Model B has CPOPF planning factors of 0.50 and 0.80 for direct labor and machine time, respectively. Historically department G uses 24% of the direct labor and machine time for these products, while department H uses the remaining 76%. What is the machine time requirement for department H next period?
A) 5,184 hours
B) 13,680 hours
C) 14,400 hours
D) 21,600 hours
E) 16,416 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Discuss the master scheduler's objectives when developing
Q2: A master production schedule incorporates production lead
Q4: Describe what CPOPF is.
Q5: In the current period, Available-to-Promise adds _
Q6: The MPS is said to be _
Q7: In MPS terminology, what is another name
Q8: What is the formula for projected available
Q9: Consider the following partial MPS record. Beginning
Q10: Beginning Inventory + MPS Shipment - maximum
Q11: Consider the following partial MPS record. Beginning