Solved

Johnny Now, Inc

Question 21

Multiple Choice

Johnny Now, Inc. produces two different models of outhouses. Demand next period is expected to be 12,000 and 18,000 units for Models A and B, respectively. Model A has CPOPF planning factors of 0.75 and 0.60 for direct labor and machine time, respectively. Model B has CPOPF planning factors of 0.50 and 0.80 for direct labor and machine time, respectively. Historically department G uses 24% of the direct labor and machine time for these products, while department H uses the remaining 76%. What is the machine time requirement for department G next period?


A) 5,184 hours
B) 4,320 hours
C) 7,200 hours
D) 21,600 hours
E) 16,416 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions