Multiple Choice
Johnny Now, Inc. produces two different models of outhouses. Demand next period is expected to be 12,000 and 18,000 units for Models A and B, respectively. Model A has CPOPF planning factors of 0.75 and 0.60 for direct labor and machine time, respectively. Model B has CPOPF planning factors of 0.50 and 0.80 for direct labor and machine time, respectively. Historically department G uses 24% of the direct labor and machine time for these products, while department H uses the remaining 76%. What is the machine time requirement for department G next period?
A) 5,184 hours
B) 4,320 hours
C) 7,200 hours
D) 21,600 hours
E) 16,416 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q16: Discuss why a negative number in the
Q17: Engines Corp. builds two different types of
Q18: Demonstrated capacity is the _ capacity _
Q19: Which of the following is not a
Q20: What is the formula for projected available
Q22: Which of the following statements is true?<br>A)
Q23: Motorsports, Inc. builds two different types of
Q24: In an MPS record, the forecast row
Q25: Consider the following partial ATP MPS record.
Q26: Motorsports, Inc. builds two different types of