Multiple Choice
Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded: Units produced 3,100
Units sold 2,800
Machine hours required 12,800
Actual overhead costs $136,000
The combined fixed and variable overhead spending variance was:
A) $1,000 U
B) $2,000 F
C) $7,000 U
D) $3,000 F
Correct Answer:

Verified
Correct Answer:
Verified
Q8: If more direct materials were used than
Q48: The variable overhead budget variance is the
Q56: Variance analysis can be used for both
Q85: Given the following data for LXG Corporation:<br>Standard
Q86: Standard costing allows management to:<br>I. Measure performance<br>II.
Q86: Burkett Company uses a standard cost system.
Q91: Pardee, Inc. completed operations for the week
Q92: Dem Mfg. has gathered the following data
Q94: Mason, Inc. uses a standard costing system.
Q100: Expected costs per unit of input are