Multiple Choice
Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded: Units produced 3,100
Units sold 2,800
Machine hours required 12,800
Actual overhead costs $136,000
The fixed overhead production volume variance was:
A) $1,000 U
B) $2,500 F
C) $1,500 F
D) $5,000 U
Correct Answer:

Verified
Correct Answer:
Verified
Q13: The fixed overhead budget variance can be
Q57: A favourable variance in one area might
Q69: The direct materials efficiency variance tells managers
Q71: Unreasonable standards may be the cause of
Q113: A standard cost variance is a difference
Q123: At the end of the period:<br>A) All
Q140: Old Rose Nursery sells over 100 varieties
Q142: Pardee, Inc. completed operations for the week
Q143: Boulder Corporation uses a standard costing system.
Q147: Hogle Mfg. Co. uses a standard costing