Multiple Choice
During the period Richeleau produced 1,000 units of product. The flexible budget for standard costs is: Direct materials $43,000
Direct labour 67,000
Variable overhead 30,000
Fixed overhead 25,000
Variances for the period are:
Direct materials price $ 400 U
Direct materials efficiency 500 F
Direct labour price 600 F
Direct labour efficiency 200 U
Variable overhead spending 300 F
Variable overhead efficiency 100 F
Fixed overhead spending 500 F
Fixed overhead production volume 1,000 U
The actual cost of direct labour incurred was:
A) $66,200
B) $66,400
C) $66,600
D) $67,400
Correct Answer:

Verified
Correct Answer:
Verified
Q27: How do managers decide which variances are
Q36: Baldwin, Inc uses a standard job cost
Q37: Errors in the accounting records related to
Q95: Which of the following is a possible
Q96: Calculating variances is a necessary, but not
Q100: Suppose you are an accountant in a
Q101: Dem Mfg. has gathered the following data
Q102: Mason, Inc. uses a standard costing system.
Q103: Given the following account balances at the
Q120: Because managers use estimates in calculating overhead