Multiple Choice
An organization's accountant is estimating next period's total overhead costs. She performed two regression analyses, one based on direct labour hours and the other based upon machine hours. The results were:
Total overhead = $150,000 + $4 x direct labour hours
Adjusted R-square = 0.65
Total overhead = $130,000 + $5 x machine hours
Adjusted R-square = 0.77
For the next period, the accountant anticipates using 28,000 direct labour hours and 26,000 machine hours. Based upon this information, what is the best estimate for overhead for the next period?
A) $262,000
B) $260,000
C) $254,000
D) $270,000
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Simple regression analysis output produces a variety
Q12: Past cost information, although accurate in predicting
Q13: The best source for determining historical costs
Q14: Bava Company wants to develop a
Q15: Assuming that a cost is mixed and
Q17: Managers should be trained in engineering to
Q18: All of the following are examples of
Q19: Simple regression minimizes the distance from each
Q20: Bava Company wants to develop a
Q21: Tom and Mike are installing new flooring