Multiple Choice
Which of the following is an advantage of using agile techniques over the SDLC?
A) A working version of the product is delivered frequently during the project.
B) Changes in systems requirements are incorporated towards the end of the project.
C) In projects using agile techniques,customers test only the completed version of the product.
D) System design is completed at the beginning of the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q20: The systems development life cycle (SDLC)generates value
Q20: Agile development techniques assume that the development
Q24: Designing only the portions of the system
Q25: Which of the following is a characteristic
Q26: The function of a scrum master is
Q27: Which of the following statements indicates why
Q32: Who are considered scrum members?
Q37: The systems development life cycle (SDLC) processes
Q43: Agile development methodologies are applicable only to
Q43: According to agile development methodologies,testing never involves