What Is the Secondstep in the Activity Analysis Process Used

Question 45

Multiple Choice

What is the secondstep in the activity analysis process used to implement Activity Based Management?


A) Chart,from start to finish,the activities used to complete the product or service.
B) Classify activities as value-added or non-value-added.
C) Eliminate non-value-added activities.
D) Continuously improve and reevaluate the efficiency of value-added activities or replace them with more efficient activities.