Multiple Choice
When one of the parties fails to perform their obligations under the contract at the time agreed, this is called an:
A) Actual breach.
B) Total breach.
C) Failure to comply.
D) Anticipatory breach.
Correct Answer:

Verified
Correct Answer:
Verified