Exhibit 17-1 in 2014, Omega Construction Began Work on a Contract

Question 82

Multiple Choice

Exhibit 17-1 In 2014, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows: Exhibit 17-1 In 2014, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:    -Refer to Exhibit 17-1. Under the percentage-of-completion method of revenue recognition, the net amount reported for construction in progress inventory at the end of 2015 would be A)  $ 87,600 B)  $189,600 C)  $210,000 D)  $312,000
-Refer to Exhibit 17-1. Under the percentage-of-completion method of revenue recognition, the net amount reported for construction in progress inventory at the end of 2015 would be


A) $ 87,600
B) $189,600
C) $210,000
D) $312,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions