Multiple Choice
Exhibit 17-2 The following information relates to a project of the Cumberland Construction Company:
The contract price was $1,000,000. Cumberland used the percentage-of-completion method of revenue recognition.
-Refer to Exhibit 17-2. What amount of gross profit was recognized in 2014?
A) $150,000
B) $ 28,571
C) $ 24,000
D) $ 20,400
Correct Answer:

Verified
Correct Answer:
Verified