Cycle time includes:
A) Processing time,storage and waiting time,movement time,and inspection time.
B) Processing time,inspection time,and inventory time.
C) Processing time,storage and waiting time,finishing time,and selling time.
D) Processing time,storage and waiting time,movement time,and finishing time.