Scott Enterprises Is Considering a Project That Has the Following

Question 33

Multiple Choice

Scott Enterprises is considering a project that has the following cash flow and WACC data.What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected.
Scott Enterprises is considering a project that has the following cash flow and WACC data.What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected.   A)  $77.49 B)  $81.56 C)  $85.86 D)  $90.15 E)  $94.66


A) $77.49
B) $81.56
C) $85.86
D) $90.15
E) $94.66