Multiple Choice
The percentage-of-completion method
A) is affected by the actual schedule of cash collection.
B) cannot be used if the contract specifies that the contractor will receive the entire contract price only on completing construction.
C) measures the proportion of total work carried out during the accounting period either from engineers' estimates of the degree of completion or from the ratio of costs incurred to date to the total costs expected for the entire contract.
D) is not a method allowed by U.S.GAAP.
E) none of the above.
Correct Answer:

Verified
Correct Answer:
Verified
Q42: Operating risks<br>A)include variability in sales from changing
Q43: When a firm decides that a particular
Q44: The firm may transfer the accounts receivable
Q45: In estimating the amount of uncollectible accounts
Q46: A firm that transfers its receivables in
Q48: Sales returns affect net cash collections when
Q49: The percentage-of-completion method<br>A)recognizes a portion of the
Q50: The allowance method for uncollectibles is used
Q51: The sales, all on account, of
Q52: U.S.GAAP requires that the completed contract method