Solved

In Year 1, Southern Construction Agrees to Construct a School  Year 1 Year 2\text { Year } 1 \quad \text { Year } 2

Question 122

Multiple Choice

In year 1, Southern Construction agrees to construct a school building for $12,000,000, receiving payments for the work of $6,000,000 in both year 1 and year 2.Southern estimates that the costs will be $4,000,000 in Year 1 and $6,000,000 in Year 2.If Southern uses the percentage-of-completion method (based on total costs) , what amount of profit is recognized in each year of the contract?
 Year 1 Year 2\text { Year } 1 \quad \text { Year } 2


A) $0$2,000,000\$ 0 \quad \$ 2,000,000
B) $2,000,000$0\$ 2,000,000 \quad \$ 0
C) $1,000,000$1,000,000\$ 1,000,000 \quad \$ 1,000,000
D) $800,000$1,200,000\$ 800,000 \quad \$ 1,200,000
E) $2,000,000$1,000,000\$ 2,000,000 \quad \$ 1,000,000