    When John Sets Deadlines for an Upcoming Project, He Is
Solved

When John Sets Deadlines for an Upcoming Project, He Is

Question 169

Question 169

Multiple Choice

When John sets deadlines for an upcoming project, he is using ______ planning.


A) operational
B) tactical
C) strategic
D) contingency

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q66: Compare the four types of organizational structures.

Q73: Empowerment is an important part of democratic

Q164: Autocratic is a leadership style that adjusts

Q166: In a line organization, the staff manager

Q168: Which managers typically implement a strategy?<br>A) middle

Q170: Complete the following using the terms listed

Q171: Ramon's job is to establish performance standards,

Q172: Danielle runs a restaurant and gives her

Q173: Leadership involves the use of power.

Q174: A(n) _ can help clarify the structure

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines