Multiple Choice
The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: What is the amount of the factory overhead controllable variance?
A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q75: If the standard to produce a given
Q76: Standard costs can be used with both
Q77: Variances from standard costs are usually reported
Q78: The following data is given for the
Q79: The following information relates to manufacturing overhead
Q81: Standards that represent levels of operation that
Q82: The formula to compute direct labor rate
Q83: The standard costs and actual costs for
Q85: Japan Company produces lamps that require 2.25
Q129: A budget performance report compares actual results