Multiple Choice
Reference - Earthquake. Stewart, the owner of ABC Construction, agreed with Joan, the owner of XYZ Hotel that he would complete renovations on her upper scale hotel on the beach in Florida by October 1. The amount due to Stewart under the contract was $250,000. The contract contained a clause by which Stewart would pay Joan $50,000 for each day he was late on completing the project. Unfortunately, an unexpected strong earthquake shook the area; and while the earthquake did not damage the hotel itself, Stewart encountered significant difficulty in getting supplies due to the high demand for building material following the earthquake. Because he believed that traveling, himself, to other states to obtain supplies would be prohibitively expensive, he delayed the project for two weeks while waiting for local stores to have sufficient supplies available. Stewart finished renovations six days late. Joan told Stewart that she owed him nothing but that he owed her $50,000. Stewart told Joan that he was suing for the entire $250,000 because it was not his fault the earthquake delayed matters. Which of the following is the appropriate term for the agreement that Stewart would pay Joan $50,000 for each day he was late in completion?
A) Mitigated damages term
B) Liquidated damages clause
C) Stipulated damages
D) Acknowledged damages clause
E) Approved and acknowledged damages clause
Correct Answer:

Verified
Correct Answer:
Verified
Q2: From what country did equitable remedies,as applied
Q24: An offer of performance by being ready,willing,and
Q30: Which of the following types of damages
Q56: Which of the following is a type
Q57: Under the UCC, when may orders for
Q60: Which of the following is a way
Q62: Reference - Dream Home. Maurice finds a
Q65: Reference - Powder Room Mess. For $300,000,
Q66: Yolanda and Rodney agreed that Rodney would
Q66: A _ occurs whenever a party fails