Multiple Choice
Cost-reimbursement contracts are most appropriate for projects that
A) take less than one year to complete.
B) are with customers that want a single payment date.
C) are well defined and entail little risk.
D) involve risk.
Correct Answer:

Verified
Correct Answer: