Brierton Company enters a contract at the beginning of year 1 to build a new federal courthouse for a price of $16 million. Brierton estimates that total cost of the project will be $12 million, and will take four years to complete.
-If Brierton used percentage-of-completion method to account for this project, what would they have reported as profit in year 2?
A) $ 0
B) $ 1.333M
C) $ 1.5M
D) $ 0.667M