Multiple Choice
An activity in a network diagram cannot start until
A) all of the preceding activities that are linked to it by arrows are finished.
B) most of the preceding activities that are linked to it by arrows are finished.
C) none of the preceding activities that are linked to it by arrows are finished.
D) at least one of the preceding activities that are linked to it by arrows are finished.