Multiple Choice
Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.
A) The activities using the limited resources are shown in a ladder relationship as they are available.
B) The activities using the limited resources are shown in a loop relationship as they are available.
C) The activities requiring the limited resource are assigned at different times.
D) If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources.
Correct Answer:

Verified
Correct Answer:
Verified
Q27: Resource-limited scheduling will not extend the project
Q28: The resource requirements plan illustrates<br>A) the utilization
Q29: The start of noncritical activities are delayed
Q30: If three activities are using the same
Q31: When several activities need the same limited
Q33: Resource leveling, or smoothing, levels the resources
Q34: Which of following would allow for level
Q35: _ is an iterative method in which
Q36: In addition to showing the technical constraints
Q37: Why are activities drawn in a serial