Resource Leveling, or Smoothing, Is a Method for

Question 21

Multiple Choice

Resource leveling, or smoothing, is a method for


A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) extending the project to have the least number of resources used per day.