The Start of Noncritical Activities Are Delayed Beyond Their Earliest

Question 29

Multiple Choice

The start of noncritical activities are delayed beyond their earliest start times (but not beyond their latest start times) in order to


A) schedule with a technical constraint.
B) schedule with a resource constraint.
C) level the costs of the project.
D) maintain a uniform level of required resources.

Correct Answer: