The audit planning meeting must
A) take place before the client acceptance decision is made.
B) be attended by the entire core engagement team and the predecessor auditors.
C) establish an understanding among the members of the audit team about the objectives of the audit.
D) prepare the internal auditors for the work they will be asked to perform to supplement the auditor's procedures.
Correct Answer:

Verified
Correct Answer:
Verified