In ____, a Full-Time Project Manager Has Complete Project and Administrative

Question 22

Multiple Choice

In ____, a full-time project manager has complete project and administrative authority over the project team.


A) an autonomous project organizational structure
B) a functional organizational structure
C) a matrix organizational structure
D) a project management office

Correct Answer: