Multiple Choice
Rite Contractors,Inc.,agrees to build a motel for Sleep Inn Corporation.The project proceeds according to plan,but before it is done,Sleep tells Rite to quit.Rite may recover
A) the contract price less costs of materials and labor.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.
Correct Answer:

Verified
Correct Answer: