In a PERT Network, the Critical Path Is the __________

Question 6

Multiple Choice

In a PERT network, the critical path is the __________.


A) central guideline that other activities feed in to
B) checkpoint for comparing standards of completion
C) most time-consuming sequence of events and activities
D) most costly path in the project schedule
E) quickest and most direct route to project completion

Correct Answer: