Scheduling Tools (Scenario)
Grace has just graduated from university and is totally overwhelmed by her first management job. When she was in school, she could work on projects one at a time; but now she must juggle several projects, each of which has multiple activities. Grace is amazed to find that her supervisor, Linda, has everything planned in a flow chart diagram. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the major activities and potential problems so that she can be more proactive.
-To help get organized, Grace prepares a bar graph that visually shows when her tasks are supposed to be done and compares that with the actual progress on each. Now she can easily assess which projects are ahead of, behind, or on schedule. Grace has used which scheduling technique?
A) PERT network analysis
B) Gantt chart
C) linear programming
D) load chart
E) time series analysis
Correct Answer:

Verified
Correct Answer:
Verified
Q72: The Gantt chart is a bar graph
Q73: Environmental scanning is the screening of large
Q74: Refer to the scenario below to answer
Q75: The intent of scenario planning is to
Q76: Refer to the scenario below to answer
Q78: Refer to the scenario below to answer
Q79: Refer to the scenario below to answer
Q80: Three techniques that help managers assess their
Q81: The task of getting a project's activities
Q82: Time series analysis, substitution effect, and economic