Multiple Choice
If a manager investigates how and why performance has deviated beyond the acceptable range of variation, and then corrects the source of the deviation, she is using ________.
A) bureaucratic control
B) immediate corrective action
C) basic corrective action
D) concurrent control
E) feedforward control
Correct Answer: