Multiple Choice
Which of the following is true about contingency funds?
A) Contingency funds are funds set aside by the client to address unforeseen events that cause the project costs to increase.
B) Projects with a high risk profile will typically have a small contingency budget.
C) Contingency is typically managed as multiple line items in the project budget.
D) Allocating the contingency budget to the items in the budget that have low risk allows the project team to track the use of contingency against the risk plan.
E) The availability of contingency funds in the line item budget may increase the use of contingency funds to solve problems rather than finding alternative solutions.
Correct Answer:

Verified
Correct Answer:
Verified
Q32: Risk sharing involves partnering with others to
Q33: The possible loss that is associated with
Q34: What are the elements of risk management
Q35: The purchase of insurance on certain items
Q36: _ includes both the identification of potential
Q38: Risks that can be anticipated, such as
Q39: High scores for environmental complexity imply high
Q40: The _ is the plan to reduce
Q41: According to David Parker and Alison Mobey's
Q42: During the closeout phase, _.<br>A) risks must