Multiple Choice
Contractual agreements with vendors can be managed more conveniently if the unit of measure for partial completion is the same as that used for _____.
A) resource planning
B) cost control
C) cost budgeting
D) cost aggregation
E) cost estimating
Correct Answer:

Verified
Correct Answer:
Verified