    _____ Is the Money Held to Pay for Predictable but Unspecified
Solved

_____ Is the Money Held to Pay for Predictable but Unspecified

Question 17

Question 17

Multiple Choice

_____ is the money held to pay for predictable but unspecified extra costs.


A) Planned reserve
B) Surety reserve
C) Contingency reserve
D) Management reserve
E) Budget reserve

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q12: The methods used to estimate the cost

Q13: Which is the most accurate and time-consuming

Q14: The term _ refers to the budgeted

Q15: The process of matching funds provided with

Q16: Unlike management reserves, contingency reserves are not

Q18: Measures such as percentage of activities completed

Q19: If the money needed to pay for

Q20: The detailed cost estimates for each activity

Q21: The schedule variance is the difference between

Q22: If a project consists of activities that

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines