Multiple Choice
Which of the following is true about estimations of activity durations?
A) The person responsible for the work will most likely exclude extra time.
B) The person with the most knowledge is the most objective person to provide duration estimates.
C) The larger and more complex the project, the greater the need for detail, which usually translates into longer durations for activities.
D) Multiple inputs into the duration estimate increase bias.
E) The accuracy of an estimate is related to the quality of the knowledge and how that knowledge is applied.
Correct Answer:

Verified
Correct Answer:
Verified
Q62: Describe the Gantt chart.
Q63: To consider the availability of team members,
Q64: The amount of time that must separate
Q65: Project managers can divert some resources from
Q66: Describe the different types of project schedules.
Q68: The process of deriving conclusions based on
Q69: Describe how project managers can accelerate the
Q70: The unit of measure that is chosen
Q71: Which of the following types of software
Q72: Identify the features that should be considered