An) _____ Is the Soonest Date an Activity Can Begin

Question 47

Multiple Choice

An) _____ is the soonest date an activity can begin as determined by the project start date and the durations of its predecessor activities.


A) early start date
B) negative float
C) free float
D) critical path
E) milestone

Correct Answer: