Multiple Choice
An) _____ is the soonest date an activity can begin as determined by the project start date and the durations of its predecessor activities.
A) early start date
B) negative float
C) free float
D) critical path
E) milestone
Correct Answer:

Verified
Correct Answer:
Verified